Royal Wolf BAC
Brisbane Airport 4008
Bulk earthworks | Pavement Works
CLIENT: McNab
Removal of 40,000 tonnes of unsuitable material and installation of 10,000m3 fill to achieve bulk earthwork level. Facing the risk of differential settlement between pre-load and non-preload areas of site, Blend installed load transfer platforms to allow for ground improvement before completing roadbase working platforms to the balance.
Scope
-
Cut to waste of 37,500t of unsuitable material
Cut/import fill of 10,000m3
Final trimming and proof rolling to 37,000m2 of structural platform
-
Roadbase load transfer platform installation for piling works and ground stabilisation (6,000m3)
Roadbase installation to building platform, working platforms and site capping layer (6,000m3)