redlands Hospital MLCP
Redlands 4163
Ground remediation | Civil
CLIENT: Woollam
Following Redcliffe and Logan Hospitals, Redlands Hospital was the third multilevel carpark Blend completed. Over 30,000m3 of unsuitable fill was removed from site in order to achieve level 1 certification.
Scope
-
Construction of 200m all-weather road (quarry rock) for project access
Construct 300m2 temporary asphalt car parking
Clearing and grubbing
-
Over-excavation and removal of 30,000m3 of inert/unsuitable material
Installation of bridging material to span unsuitable subgrade
-
Import, place, spread & compact general fill
Final trimming to underside of slab
Level 1 certification
-
Excavation of band beam footings (3,500m3)
Load, haul & dispose of unsuitable material from band beam excavation