Gateway Industrial Park
Murarrie 4172
DEMOLTION
CLIENT: Centennial
Demolition and disposal of 12,000m2 (GFA) of cold rooms, portal shed structures, topping slab and associated insulation foam layer. By thinking outside the box and developing a unique methodology for slab demolition, Blend was able to ensure adequate separation of foam from concrete for later crushing into 28mm minus recycled roadbase.
Scope
-
Removal of 12,000m2 bonded and friable asbestos sheeting
Demolition and disposal of 12,000m2 insulated cold-store rooms
Demolition and disposal of 16,000m2 topping slabs and associated underslab insulation - separated and stockpiled on-site for crushing to roadbase